Russian projects

Novy Port

Yamal Peninsula



Gazprom Neft’s share

To be commissioned > Design capacity to be reached

90% 100% consolidation by output.

2016 > 2020


2P hydrocarbon reserves (PRMS classification) (mtoe) (Including the Company’s share in the project)

240.13
(146.66 + 93.47)

Hydrocarbon production in 2018 (mtoe) 2019F

10.79
13.03

Design capacity (mtpa)

8.6

2018 milestones


  1. Two escorting icebreakers – Alexander Sannikov and Andrey Vilkitsky – joined the Arctic fleet.
  2. Key design solutions were approved to develop the northern section of the Novoportovskoye oil and gas condensate field; pilot production phase completed.
  3. Key specifications were approved for a gas pipeline to cross the Gulf of Ob; design phase started.

Plans for 2019


  1. Design documents were developed to expand production infrastructure into the northern section of the field; final investment decision made.
  2. Phase 2 of the oil collection and treatment infrastructure completed.
  3. The final investment decision was made to build a gas pipeline; construction started onshore and offshore the Gulf of Ob.

Messoyakha (VMLB)  Vostochno-Messoyakhsky licence block.

Tazovsky district, Yamal-Nenets Autonomous District



Gazprom Neft’s share

To be commissioned > Design capacity to be reached

50%

2016 > 2021


2P hydrocarbon reserves (PRMS classification) (mtoe) (Including the Company’s share in the project)

65.11
(15.01 + 50.10)

Hydrocarbon production in 2018 (mtoe) 2019F

2.30
2.81

Design capacity (mtpa)

5.9

2018 milestones


  1. Construction of APG utilisation infrastructure started by way of gas re-injection.
  2. Geological surveys completed for a section of the Zapadno-Messoyakhsky licence block to be used as a temporary underground gas storage; possibility of gas injection confirmed.
  3. Multi-frac efficiency confirmed for PK 1-3 unconsolidated reservoir.
  4. Flooding management technique introduced.

Plans for 2019


  1. Construction of gas re-injection infrastructure; delivery of equipment (GPA-2 gas compressor unit, a low temperature separation unit, and a turbo-expander) for the GAS project.

Kuyumba

Krasnoyarsk Territory



Gazprom Neft’s share

To be commissioned > Design capacity to be reached

50%

2018 > 2032


2P hydrocarbon reserves (PRMS classification) (mtoe) (Including the Company’s share in the project)

252.14
(22.90 + 229.24)

Hydrocarbon production in 2018 (mtoe) 2019F

0.25
0.81

Design capacity (mtpa)

10.7

2018 milestones


  1. Commercial production started at the Kuyumbinskoye field.
  2. Central gathering facility commissioned and operating.
  3. Project re-framed, with priority drilling areas identified.

Plans for 2019


  1. Expansion of the central gathering facility to be capable of processing 2.9 mtpa of oil.
  2. Government review of the project design documents for the pipeline to connect the modular unit for initial water separation of the Tersko-Kamovsky licence block and the central gathering facility of the Kuyumbinsky licence block.
  3. Commissioning of the oil and gas pipeline connecting the Podkamennaya Tunguska oil and gas collecting pipe and the central gathering facility commissioned.
  4. Business case for the Tersko-Kamovsky licence block to be confirmed.

Tazovsky

Tazovsky district, Yamal-Nenets Autonomous District



Gazprom Neft’s share

To be commissioned > Design capacity to be reached

100%

2021 > 2021


2P hydrocarbon reserves (PRMS classification) (mtoe) (Including the Company’s share in the project)

49.02
(37.75 + 11.27)

Hydrocarbon production in 2018 (mtoe) 2019F

0.17
0.20

Design capacity (mtpa)

2

2018 milestones


  1. Investments into the implementation phase approved.
  2. 13 wells, including 2 high-tech wells, drilled.
  3. Engineering surveys for on-site facilities and pipelines completed.

Plans for 2019


  1. Reserves to be re-estimated by the end of 2019.
  2. Delivery of certain long-lead equipment, including a modular oil treatment unit.
  3. Construction of infrastructural facilities.

Otdalennaya group of fields (OGF)

Yamal-Nenets Autonomous Area



Gazprom Neft’s share

To be commissioned > Design capacity to be reached

100%

2018 > 2021


2P hydrocarbon reserves (PRMS classification) (mtoe) (Including the Company’s share in the project)

24.53
(9.52 + 15.01)

Hydrocarbon production in 2018 (mtoe) 2019F

0.84
1.31

Design capacity (mtpa)

1.60

2018 milestones


  1. Laboratory and in-office geochemical surveys completed for phase 1 of the Vorgensky licence block project.
  2. 3D seismic cube processed and interpreted.
  3. Long-term exploration programme developed.
  4. Well 711PO completed and tested at the Zapadno-Chatylkinsky licence block.

Plans for 2019


  1. Completion and testing of Well 42 at the Yuzhno-Udmurtskoye field.
  2. Completion of field surveys and geochemical data interpretation for phase 2 of the northern section of the Vorgensky licence block.
  3. Completion and testing of three exploration and appraisal wells (780PO, 743PO, 746PO).
  4. Presentation to the steering committee; phase 3.3 moving from Exploration to Appraisal; decision on the further development of phase 3.3.
  5. Suggestions for the exploration programme based on the basin modelling results.

Prirazlomnoye (Offshore project)

Offshore the Pechora Sea



Gazprom Neft’s share

To be commissioned > Design capacity to be reached

100%

2013 > 2024


2P hydrocarbon reserves (PRMS classification) (mtoe) (Including the Company’s share in the project)

55.35
(31.84 + 23.51)

Hydrocarbon production in 2018 (mtoe) 2019F

3.24
3.29

Design capacity (mtpa)

4.80

2018 milestones


  1. 3 new wells commissioned.

Plans for 2019


  1. Commissioning of new wells.
  2. Commissioning of a helipad and an OSR site.
  3. Project design for phase 2 retrofitting of the Prirazlomnaya offshore ice-resistant stationary platform.